PROJECT NAME
Skavica Hydro Power Plant

INVESTOR
Albanian Power Corporation (KESH), EBRD

LOCATION
Drin River

POWER PLANT TYPE
Hydroelectric power plant

POWER
132 MW

ANNUAL PRODUCTION / REGIME
450 GWh/year

VALUE OF INVESTMENT
500 mil. EURO

PROJECT STATUS
Preparation, the construction activities are planned to start in 2020

DURATION OF RECONSTRUCTION
Unknow

Bulgaria

PROJECT NAME
5 HPPs reconstruction

INVESTOR
National Electricity Company (NEK), EBRD

LOCATION
Rila mountains

POWER PLANT TYPE
Reconstruction

POWER
Reconstruction of 864 MW Chaira Pumped Storage Hydro Power Plant
75 MW Belmeken PSHPP
240 MW Sestrimo HPP
120 MW Momina Klisura HPP
14 MW Vacha-1 HPP
110 kV switchyard and other HPP systems of integrated control

VALUE OF INVESTMENT
37 mil. EURO

PROJECT STATUS
In preparation

DURATION OF RECONSTRUCTION
Unknow

Croatia

PROJECT NAME
Kosinj/Senj

INVESTOR
HEP (Croatian Electric Power)

LOCATION
Kosinj, Gusić polje, Grabovac

POWER PLANT TYPE
Hydroelectric power plant, storage high pressure plant

POWER
412 MW

ANNUAL PRODUCTION / REGIME
increase by 320 GWh (system total: 1.5TWh) / peak power plant

VALUE OF INVESTMENT
500 mil. EURO

PROJECT STATUS
Project started in 2018 and is in progress

DURATION OF RECONSTRUCTION
6 years

Montenegro

PROJECT NAME
Komarnica

INVESTOR
Montenegro’s electricity company, Elektroprivreda Crne Gore (EPCG)

LOCATION
Komarnica river, canyon Nevidio

POWER PLANT TYPE
Peak hydro power plant, with the dam

POWER
172 MW

ANNUAL PRODUCTION / REGIME
227 GWh/year

VALUE OF INVESTMENT
178 mil. EURO

PROJECT STATUS
Preparation, preliminary design plan

DURATION OF RECONSTRUCTION
7 years